By the end of this month, the goals of the Big Construction project should be 95% complete,
Tuesday, December 8, 2020


By the end of this month, the goals of the Big Construction project should be 95% complete, Kyrylo Tymoshenko, deputy presidential chief of staff, tells Interfax-Ukraine. The completion scorecard is: 200 schools and kindergartens: 93% complete; 4,000 km of state roads: 92% complete: and 100 sports facilities – 87% complete. For schools, the construction means new buildings for 8,338 students and renovated buildings for 55,000 students.