On Wednesday, The World Bank approved a $212 million in low interest loans to help Ukraine synchronize its electricity system with the EU’s ENTSO-E power grid by 2024

Friday, July 2, 2021

. The Bank reports that loans to Ukrhydroenergo will help pay for 197-megawatt short-duration battery energy storage systems combined with solar power plants at four hydroelectric dam sites on the Dnipro — Kyiv, Kaniv, Kremenchuk and Kamianske. In addition, a long-duration battery and solar power plant will be installed at Dnister Hydroelectric Plant.

Support independent journalism team

Dear Ukraine Business News reader, we are a team of 20 Ukrainian journalists, researchers, reporters and editors who would humbly ask for your support.

Previous post

“It will help Ukraine integrate its power system with the European power grid,